Resource Group Sequencing
This form allows you change the sequence of scheduled jobs and operations for the selected resource group, after running the Scheduling activity. If no resources in the group have been allocated to any loads, or if the Dispatch Intervals value is set inappropriately, the message "Not one Sequence Exists" displays.
Your changes will be reflected on the Resource Group Dispatch List report, but are discarded the next time you run the Scheduling activity.
The Resource Group Sequencing form does not indicate any specific resources from the selected group. To resequence a specific resource, use the Resource Sequencing form.