Delay Detail APS
This form provides a focused view, using APS Planner data only, of the delays associated with a particular demand. Use this form in conjunction with the Demand Detail Chart APS form to obtain a complete view of critical delays and their causes.
After filtering by the delay types you would like to see, the grid at the bottom of the form displays information related to the selected delays. For item delays, the grid displays all supplies used to satisfy the component demand that is delaying this operation. For resource group delays, the grid displays utilization information for all resource groups required by the operation between the earliest start date and the planned end date. That time period will be broken into analysis intervals (days or weeks, depending on the total duration), with a row for each interval.
The
selection is accessible from the menu.