Creating Outside Operations
If the actual work on an operation is performed at a location other than your shop floor, you must perform special steps to capture the status of the operation for accurate APS, scheduling, and costing. If you do not represent and manage an outside operation properly, the effects can ripple down through subsequent processes, resulting in an over-conservative plan and schedule.
To capture outside operation status, you can:
- Use the Post Job Transactions form to post time or quantity remaining on the operation (the Operation Scheduling parameter on Shop Floor Control Parameters determines whether hours or pieces remaining are posted). You must specify the operation's work center as "Outside" on the Scheduling tab on the Work Centers form. Use this method only if you have accurate status information for the outside operation.
- Cross reference the outside operation to one or more purchase order line items. Time remaining on the operation is calculated using the purchase order line item due dates.
Because you may not necessarily have accurate information to post time or quantity remaining for an outside operation, we recommend you model outside operations using the cross-referenced purchase order method (although you can use that method and also post time or quantity to the operation if you have the status information).
This topic describes how to set up the cross-referenced purchase order method.
-
To set up the outside operation, you must create a purchased material
and issue it to the operation. Follow these steps:
-
To process the outside operation:
- Use the Purchase Order Receiving form to receive the outside materials from the vendor.
- The receipt transaction automatically opens the Job Material Transactions form. On this form, issue the materials to the job.
- After you issue the materials, the Post Job WIP Move Transactions form opens automatically. On this form, record this operation complete and move the materials to the next operation.