Running MRP Planning
Run this activity only at times when no other users will be saving changes to records that are included in the plan. You can run it on a recurring basis by scheduling it on the Background Queue.
Follow these steps to run the MRP plan, which deletes the existing plan and recreates it using the latest requirements, receipts, and on-hand inventory information.
- If you change any of
these planning parameters, the system selects the
Regeneration option
automatically:
- Use CO or Forecast
- Check PO Requisitions
- Forecast Look Ahead/Look Behind
- PO Reschedule Tolerance
- Job Reschedule Tolerance
- Shrink Factor (Items form)
- Scrap Factor (Items form)
- Minimum Hours in Work Day
- MDAY Start/End
- 30-Day Bucket Fence
- 90-Day Bucket Fence
The system also selects the Regeneration option when you:
- Change the holidays on the Holidays form
- Change the default shift on the Scheduling Shifts form
- Change the Dedicated Inventory field on the Warehouses form
- Change the Transit Time on the Inter-Site Parameters form
- The forecast will not
consider orders that are stopped, planned, or credit held, if the corresponding
flags are deselected. A forecast of 400 with an order of 50 that is stopped and
the flag set to false will create a forecast plan of 400.A forecast of 400 and
an order of 50 that is stopped and the flag is set to true will have the
customer order planned and 350 planned in the forecast the net planned will be
equivalent.
APS alternate plans do not maintain this relationship. A forecast planned job will be created as defined by the production plan for use in the "What if Analysis".This has the potential, if the alternate planning parameters are set differently for a planned customer order and a forecast planned order, to duplicate the requirement, or not show any planned requirement in the alternate.