Plan Materials at Operation Start

This field applies to MRP and APS.

When the system is planning released jobs and production schedule releases, this field controls whether the materials for a job or production schedule release are required to be available at the operation's start date or at the job/PS release start date.

  • Select this field to plan the materials to be due at the start of the operation in which the materials are used. This method of planning results in a just-in-time material plan. In most cases (especially if you are using APS), you should select this field.
  • Clear this field to plan the materials to be due at the start of the job/production schedule. Typically, you should clear this field only if these conditions are true:
    • you want to have all materials ready before you release the job or PS release
    • all of the materials are not specified on the first operation in the routing.
Note: 
  • Planned production schedule releases are only affected by this parameter if the planning parameter, Plan Planned Production Schedules, is selected.
  • This field also determines how requirements are displayed on the Time Phased Inventory Status form and on the Purchase Requirements Report.